Post grouting technology and its influence on the bearing capacity of bored piles
CSTR:
Author:
Affiliation:

1.Tianjin North China Geological Exploration Bureau;2.Tianjin Huakan Foundation Engineering Testing Co., Ltd

Clc Number:

TU473.1 4

  • Article
  • | |
  • Metrics
  • |
  • Reference [15]
  • |
  • Related [20]
  • | | |
  • Comments
    Abstract:

    This paper studies a field case where post grouting technology failed to greatly improve the bearing capacityof the single pile, and concludes that the main cause for the insufficient bearing capacity of the single pile is the poor control of the grouting process. Strict quality control and installation of the grouting pipe, jet grouting pipe and check valve as well as the grouting process control are the key factors for successful grouting, hence improvementof the bearing capacity. In the above field case, the area with insufficient bearing capacity was treated by supplementary piles. During construction of the supplementary piles, the production of the grouting device was standardized and the control of the grouting process was strengthened. After the supplementary piles reached the agingperiod, the static load test was carried out, and the results showed that the bearing capacity of the supplementarypiles met the design requirements.

    Reference
    [1]郑楷.北京市某超高层建筑基础灌注桩后压浆技术的研究与应用[D].吉林长春:吉林大学,2013.
    [2]夏群.超高层建筑中钻孔灌注桩后注浆技术分析及其应用[J].工程勘察,2012,(11):37-43.
    [3]张慧.后压浆灌注桩在天津超高层建筑基础中的应用分析[J].探矿工程(岩土钻掘工程),2018,45(3):84-89.
    [4]郑楷,赵大军,隗延龙,等.灌注桩后注浆对沉降影响的数值分析[J].施工技术,2016,45(7):66-69.
    [5]周志刚.后压浆灌注桩承载性状研究及应用[D].北京:中国地质大学(北京),2018.
    [6]万志辉, 戴国亮, 龚维明,等.超厚粉细砂地层组合压浆桩压浆效果试验[J]. 中国公路学报,2018,31(3):59–67.
    [7]万志辉,戴国亮,王磊,等.黏性土层中后压浆桩承载性状的对比试验研究[J].岩土工程学报,2018,40(增2):194-198.
    [8]WAN Z H, DAI G L, GONG W M. Full-scale load testing of two large diameter drilled shafts in coral-reef limestone formations[J]. Bulletin of Engineering Geology and Environment, 2018, 77(3): 1127–1143.
    [9]孙凤玲,刘焕存,刘涛.武汉某摩擦型灌注桩后注浆单桩竖向承载力实验研究[ J ] . 探矿工程(岩土钻掘工程),2018,45(5):63-66.
    [10]李东海,陈奕柏,谢洪波,等.滨海软弱地基钻孔钻孔灌注桩抗压承载力失效分析[J].施工技术,2016,45(9):111-114.
    [11] 焦文秀.泥浆护壁成孔灌注桩后压浆技术正确应用研究[J].探矿工程(岩土钻掘工程),2018,45(7):87-89.
    [12] 何一鸣,万志辉,邓会元,等.后压浆单桩室内长期承载性能试验研究[J].施工技术,2017,46(19):72-75.
    [13] JGJ106-2014,建筑基桩检测技术规范[S].
    [14] 胡胜华,张所邦,韩朝,等.灌注桩后压浆技术的工程实践[J].探矿工程(岩土钻掘工程),2014,41(12):71-74.
    [15] 孟宝华,邓宇,徐俊.旋挖成孔灌注桩后注浆工艺在成都京东方桩基工程中的应用 [J].探矿工程(岩土钻掘工程),2016,43(11):84-87.
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:February 14,2020
  • Revised:April 04,2020
  • Adopted:April 24,2020
  • Online: August 13,2020
Article QR Code