Tube well dewatering technology for repair of the water intake tunnelunder the Yangtze River
DOI:
CSTR:
Author:
Affiliation:

1.The First Institute of Hydrology and Engineering Geological Prospecting Anhui GeologicalProspecting Bureau, Bengbu Anhui 233000, China;2.Anhui Hydrogeology and Engineering Geology Company, Bengbu Anhui 233000, China;3.Large Diameter Shield Co., Ltd. of China Railway Bureau 14 Group, Nanjing Jiangsu 210031, China

Clc Number:

TU46 3

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    In the process of shield excavation of the water intake tunnel for a power plant in the south of Jiangsu, the confined water flooded the tunnel with sediments due to a gas kick. It was necessary to prevent the confined water from surging out again during the tunnel repair. Whether the water level of the massive confined aquifer under the Yangtze River can be reduced by the tube well caused a great controvesy. Base on the analysis of hydrogeological conditions and field pumping tests, the hydraulic connection between the objective aquifer with the river water and the lower massive confined aquifer was found, the hydrogeological parameters of each layer was calculated, a reliable dewatering scheme was provided, and the subsidence deformation was predicted and analyzed. It also has solved a series of difficult problems such as the construction of pipe wells over water, providng important reference of similar projects.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:November 24,2018
  • Revised:June 07,2019
  • Adopted:June 10,2019
  • Online: July 23,2019
  • Published:
Article QR Code