4/6/2025, 11:21:43 AM 星期日
Pumping Test and Calculation of Hydrogeological Parameters for Massive Anisotropic Phreatic Aquifers
CSTR:
Author:
Affiliation:

No.1 Institute of Hydrology and Engineering Geological Prospecting, Anhui Geological Prospecting Bureau

Clc Number:

TU46 3

  • Article
  • | |
  • Metrics
  • |
  • Reference [13]
  • |
  • Related [5]
  • | | |
  • Comments
    Abstract:

    The permeability coefficient determines the estimation of water inflow at deep foundation pits and the type of the water cutting-off curtain, and affects the safety and cost of the project; thus, it is of great significance to the construction of deep foundation pits in water-rich areas. For anisotropic aquifers, it is difficult to find a suitable method to calculate the hydrogeological parameters from the existing analytical formula, especially for the vertical permeability coefficient. A pumping test was carried out on the flow resistance by using the temporary water cutting-off curtain in the field to simulate the dewatering of foundation pits; then, the hydrogeological conceptual model and the groundwater flow mathematical model were established to invert the permeability coefficient of each layer by using a 3D finite difference numerical simulation software; finally, the model was validated by the data of verification pumping; which provided a guiding basis for the design of the envelope of a subway station in the super-thick sand and gravel stratum near the river in Fuzhou. The results of the test and the numerical simulation can be used for reference for similar projects.

    Reference
    [1] 施普德.井水量计算的理论与实践[M].北京:地质出版社,1977.2.
    [2]周志芳,汤瑞凉,汪斌;基于抽水试验资料确定含水层水文地质参数[J];河海大学学报(自然科学版);1999年03期:5-8.
    [3] 薛禹群,朱学愚等.地下水动力学[M].北京:地质出版社,1997.9.
    [4] 薛禹群,谢春红.地下水数值模拟 [M].北京:科学出版社,2007.9.
    [5] 李贵仁,赵珍,陈植华. 数值模拟在反演矿区水文地质条件中的应用[J].水文地质工程地质,2013, 40(2):19-23.
    [6]瞿成松. 邻近多条地铁的基坑降水技术[J]. 探矿工程(岩土钻掘工程), 2011, 38(2):29-35.
    [7]朱明忠, 施淑芬, 王春雨. 深井降水设计与施工若干问题探讨[J]. 探矿工程(岩土钻掘工程), 2009, 36(2):35-38.
    [8]李培妍, 宫全美, 元翔,等. 杭州某地铁深基坑减压降水措施研究[J]. 地下空间与工程学报, 2014, 10(1):213-219.
    [9]张楠. 深基坑水文地质参数的确定及降水设计[J]. 地下空间与工程学报, 2011, 07(2):375-379.
    [10]赵琳琳, 肖长来, 陈昌亮,等. 基于抽水试验的多种方法确定水文地质参数[J]. 地下空间与工程学报, 2015, 11(2):306-309.
    [11]刘清文, 车灿辉. 长江漫滩复杂地层条件下超大超深基坑降水设计[J]. 探矿工程(岩土钻掘工程), 2013(5):54-59.
    [12]Xu B, Yan C, Sun Q, et al. Field pumping experiments and numerical simulations of shield tunnel dewatering under the Yangtze River[J]. Environmental Earth Sciences, 2016, 75(8):1-16.
    [13] 中国地质调查局. 水文地质手册.第2版[M]. 地质出版社, 2012.
    Cited by
    Comments
    Comments
    分享到微博
    Submit
Get Citation
Share
Article Metrics
  • Abstract:1139
  • PDF: 1023
  • HTML: 267
  • Cited by: 0
History
  • Received:August 06,2018
  • Revised:October 23,2018
  • Adopted:October 23,2018
  • Online: November 19,2018
Article QR Code