Construction Technology of New Type Brine Recovery Well AK1
DOI:
CSTR:
Author:
Affiliation:

The Institute of Exploration Techniques, CAGS,Northeast Coalfield Geological Bureau No.103 Exploration Team,The Institute of Exploration Techniques, CAGS,The Institute of Exploration Techniques, CAGS,The Institute of Exploration Techniques, CAGS,Northeast Coalfield Geological Bureau No.155 Exploration Team

Clc Number:

P634

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The new type brine recovery well AK1 is located at the old area of Beypazari trona solution mining zone. AK1 was completed by the SDC-1500 truck mounted rig which was independently developed by the Institute of Exploration Techniques, CAGS. Special casing string was set in the borehole. Innovative negative pressure pumping method is used in AK1 to get the recovery from underground. The recovery of AK1 is more than 3 times of that from the normal production well, which has alleviated the shortage of brine supply for processing factory and improved the production efficiency.

    Reference
    Related
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:March 31,2016
  • Revised:June 15,2016
  • Adopted:June 20,2016
  • Online: October 28,2016
  • Published:
Article QR Code