Abstract:Because of complicated geological conditions and neighboring environment in the site of foundation pit of Hubei Provincial Armed Police Corps Regimental Commander Building, combined supporting method was adopted with pile anchor retaining, dry jet mixed pile and anchor wire mesh in shotcrete, so safety was ensured for construction of deep foundation pit, surrounding buildings and underground utilities. Economic and social benefits were achieved with lower cost and shorter construction period.