Drilling technology for complex formation in the south area of Baijian Iron Mine
Author:
Affiliation:

Hebei Bureau of Geology 9th Geological Brigade, Xingtai Hebei 054000, China

  • 摘要
  • | |
  • 访问统计
  • |
  • 参考文献 [18]
  • |
  • 相似文献 [20]
  • | | |
  • 文章评论
    摘要:

    邢台白涧铁矿南区地层岩石破碎、部分地层含角砾、胶结性差、漏失严重,钻探施工中存在掉块卡钻、缩径、坍塌、埋钻及孔内泥浆全部漏失等难题。通过优化钻孔结构、使用新工艺、新方法,合理选择钻进参数,采用绳索取心钻进配合预留技术套管,有效解决了上部煤系地层的坍塌问题;采用反丝套管的方法,极大地减轻了由于地层缩径、掉块引起的套管下不到位、起拔困难等风险;常规型绳索取心钻杆替代套管方法的采用,提高了含角砾、松散地层的穿过速度,减少了钻探工作量的报废,加快了施工进度;特别是高胎体双水口钻头的使用,提高了钻进效率,节约了钻探施工成本,项目得以如期完成。

    Abstract:

    The formation in the south area of Baijian Iron Mine in Xingtai is broken, containing breccia locally, and with poor cementation and serious leakage; thus, leading to some drilling problems, such as sticking due to falling stones, borehole contraction, collapse, drilling string burial, full circulation loss. By optimizing the drilling structure, using new processes and methods, properly selecting drilling parameters, using wireline core drilling plus pre-set technical casing, collapse of the upper coal measure strata was effectively eliminated. The use of reverse-thread casing greatly reduced the risks in placement of casing and pulling out of casing caused by borehole shrinkage and falling stones. The adoption of conventional wireline coring drill rods instead of casing improved the drilling speed in breccia and loose formation, reduced drilling abandonment, and sped up drilling progress. Notably, the use of the high matrix double nozzle bit improved drilling efficiency, and saved drilling construction cost, allowing the project to be completed on schedule.

    参考文献
    [1] 邓鹏,黄明勇,方青,等.贵州省旦坪铝土矿钻探施工工艺[J].钻探工程,2021,48(3):78-85.DENG Peng, HUANG Mingyong, FANG Qing, et al. Exploration drilling technology for the Danping Bauxite Mine in Guizhou province[J]. Drilling Engineering, 2021,48(3):78-85.
    [2] 张彦海,李光宏,白明.河北省沙河市白涧铁矿详查报告[R].邢台:河北省地矿局第十一地质大队,2010:13-15.ZHANG Yanhai, LI Guanghong, BAI Ming. Detailed Investigation Report of Baijian iron mine in Shahe city, Hebei Province[R]. Xingtai: 11th Geological Brigade of Hebei Bureau of Geology and Mineral Resources, 2010:13-15.
    [3] 鄢泰宁.岩土钻掘工程学[M].武汉:中国地质大学出版社,2001.YAN Taining. Geotechnical Drilling Engineering[M]. Wuhan: China University of Geosciences Press, 2001.
    [4] 李光宏,李红梅.多种钻探工艺技术在白涧铁矿区的应用实践[J].探矿工程(岩土钻掘工程),2017,44(9):49-52.LI Guanghong, LI Hongmei. Application practice of several drilling technologies in Baijian iron ore area[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2017,44(9):49-52.
    [5] 杨芳,陈师逊.深部地质钻探钻孔结构设计与施工分析[J].探矿工程(岩土钻掘工程),2019,46(11):21-26.YANG Fang, CHEN Shixun. Analysis of design and construction of deep geodrilling boreholes[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2019,46(11):21-26.
    [6] 陈风云,王虎,谷天本.小秦岭地区深部钻探钻孔结构设计[J].探矿工程(岩土钻掘工程),2011,38(7):44-46.CHEN Fengyun, WANG Hu, GU Tianben. Design of borehole structure of deep drilling in Xiaoqinling region[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2011,38(7):44-46.
    [7] 孙丙伦,孙友宏,徐良.金矿复杂地层金刚石取心钻头选型试验研究[J].探矿工程(岩土钻掘工程),2008,35(8):71-72,76.SUN Binglun, SUN Youhong, XU Liang. Research on optimizing experiment of diamond coring bit for drilling in gold mine of complex stratum[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2008,35(8):71-72,76.
    [8] 刘勇,常江华.某金矿水平绳索取心钻进钻头选型及试验分析[J].探矿工程(岩土钻掘工程),2011,38(7):73-75.LIU Yong, CHANG Jianghua. Selection of horizontal wire-line coring bit in a gold mine and the test analysis[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2011,38(7):73-75.
    [9] 熊虎林,徐龙生.泉子街地区地层可钻性分析及钻头选型[J].探矿工程(岩土钻掘工程),2019,46(2):30-34.XIONG Hulin, XU Longsheng. Formation drillability analysis and drill bit selection for the Quanzijie area[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2019,46(2):30-34.
    [10] 段鸿海,胡春跃.承德M24矿区深孔钻探钻进参数的选择分析[J].探矿工程(岩土钻掘工程),2011,38(3):17-20.DUAN Honghai, HU Chunyue. Selection analysis on drilling parameters of deep drilling in M24 Mining Area of Chengde[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2011,38(3):17-20.
    [11] 刘俊辉.成膜防塌无固相冲洗液在广西向阳坪地区复杂地层中的应用[J].探矿工程(岩土钻掘工程),2020,47(12):36-41.LIU Junhui. Drilling fluid technology for complex formation drillingin the Xiangyangping area of Guangxi[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2020,47(12):36-41.
    [12] 肖冬顺,符文,吴琼,等.青海五龙沟矿区泥岩地层冲洗液研究[J].探矿工程(岩土钻掘工程),2019,46(9):45-50.XIAO Dongshun, FU Wen, WU Qiong, et al. Drilling fluid for mudstone in Wulonggou Mine of Qinghai province[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2019,46(9):45-50.
    [13] 刘志峰.无固相冲洗液在变质岩系复杂地层绳索取心钻进中的应用[J].探矿工程(岩土钻掘工程),2017,44(4):14-18.LIU Zhifeng. Application of solid-free flushing fluid for wire-line coring in complex metamorphic rocks formation[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2017,44(4):14-18.
    [14] 郑继天,李小杰,关晓琳.水文地质钻探冲洗液的选用[J].探矿工程(岩土钻掘工程),2016,43(10):242-244.ZHENG Jitian, LI Xiaojie, GUAN Xiaolin. Selection of drilling fluid for hydro-geological drilling[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2016,43(10):242-244.
    [15] 乌效鸣,俞承城.钻孔液动压力平衡问题[J].探矿工程,1995(1):47-48.WU Xiaoming, YU Chengcheng. Balance of drilling fluid pressure[J]. Exploration Engineering, 1995(1):47-48.
    [16] DZ/T 0227—2010,地质岩心钻探规程[S].DZ/T 0227—2010, Geological core drilling regulations[S].
    [17] 汤凤林,A.Γ.加里宁,段隆臣.岩心钻探学[M].武汉:中国地质大学出版社,2009.TANG Fenglin, Kalinin A. C., DUAN Longchen. Core Drilling[M]. Wuhan: China University of Geosciences Press, 2009.
    [18] 陈兵,姚燕,张峰,等.浅论神农架地区岩溶复杂地层钻探施工技术[J].资源环境与工程,2010(4):398-400.CHEN Bing, YAO Yan, ZHANG Feng, et al. Discussion on drilling construction technology of complex karst stratum in Shennongjia[J]. Resources Environment & Engineering, 2010(4):398-400.
    引证文献
    网友评论
    网友评论
    分享到微博
    发 布
引用本文

李红梅,石逊.白涧铁矿南区复杂地层钻探施工技术[J].钻探工程,2021,48(11):30-35.
LI Hongmei, SHI Xun. Drilling technology for complex formation in the south area of Baijian Iron Mine[J]. Drilling Engineering, 2021,48(11):30-35.

复制
分享
文章指标
  • 点击次数:773
  • 下载次数: 938
  • HTML阅读次数: 2453
  • 引用次数: 0
历史
  • 收稿日期:2021-09-06
  • 最后修改日期:2021-10-31
  • 录用日期:2021-11-01
  • 在线发布日期: 2021-12-06
  • 出版日期: 2021-11-10
文章二维码