抛石、柴排和第四系沉积层成桩工艺方法与探索
CSTR:
作者:
作者单位:

安徽省地质实验研究所

中图分类号:

P634;TU473.1 4


Exploration of Pile Formation Process in Mattress, Riprap and the Quaternary Sedimentary Layer
Author:
Affiliation:

Anhui Province Geological Experiment Reserch Institute

  • 摘要
  • | |
  • 访问统计
  • |
  • 参考文献 [7]
  • |
  • 相似文献 [20]
  • | | |
  • 文章评论
    摘要:

    上海某炼油厂拟在黄浦江边码头施工可系万吨油轮的系缆墩,系缆墩采用钻孔灌注桩。在江面施工过程中遇到潮汐、抛石、柴排、漏浆和涌水等施工难题,导致工期和工程费用均用去2/3时施工仍没有取得突破性进展。经过研究探索,采用冲抓、粘土造壁、跟管和回转钻进相结合的工艺方法,成功地解决抛石层、柴排层、第四系沉积地层的成孔问题和抛石层漏失混凝土浆液问题,圆满完成施工任务。

    Abstract:

    Near Huangpu river wharf, a mooring dolphin for 10000 Tons oil tanker was planed to build by an oil refinery of Shanghai, which would be constructed with bored grouting piles. Tide, riprap, mattress, mud leakage and water gushing were experienced during the construction process. Through research and exploration, by the combination of grab, clay wall building, drilling with casing and the rotary drilling method, the difficult problems of boring in riprap, mattress and the quaternary sedimentary layer were successfully overcome with completion of the construction task.

    参考文献
    [1]DZ/T0155—95.钻孔灌注桩施工规程   中华人民共和国地质矿产行业标准.
    [2]杨宗仁,史学伟.沪—蓉高速铁路跨越汉江特大桥桩孔施工技术[J].探矿工程(岩土钻掘工程),2010,37(3):47—50.
    [3]曾定帮,彭文祥.东海大桥海上钻孔灌注桩施工技术[J].探矿工程(岩土钻掘工程),2005,32(5):31—32,36.
    [4]陈福华.砂性、粉砂性土层钻孔灌注桩施工要点[J].探矿工程(岩土钻掘工程),2006,33(11):19—20.
    [5]DG/TJ08—08—202—2007.钻孔灌注桩施工规程  上海市工程建设规范
    [6]石飞轮.江苏苏通大桥钻孔灌注桩超标PHP泥浆技术应用[J].探矿工程(岩土钻掘工程),2006,33(2):50—51。
    [7]蒋华福。上海中心大厦钻孔灌注桩施工技术 建筑技术,2010,41(9):854—857.
    引证文献
    网友评论
    网友评论
    分享到微博
    发 布
引用本文

朱效中.抛石、柴排和第四系沉积层成桩工艺方法与探索[J].钻探工程,2013,40(11):52-56.
ZHU Xiao-zhong. Exploration of Pile Formation Process in Mattress, Riprap and the Quaternary Sedimentary Layer[J]. Drilling Engineering, 2013,40(11):52-56.