大口径煤矿应用井施工技术难点及应对措施
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Technical Difficulties in Large Diameter Well Drilling in Coal Mine Construction and the Countermeasures
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    结合山东省龙固矿井煤矿应用井施工工程实际,阐述了在巨厚表土层中,无表层套管施工的优点及施工难度,并提出了应对措施:通过塔式钻具防斜、陀螺仪测斜、螺杆钻纠斜、优质泥浆护壁、浮力器平衡套管重力、气动扳手减轻工人劳动强度等措施,提前完成了2口井的施工。同时,由于无表层套管,大大降低了施工成本,节约了施工时间。

    Abstract:

    Based on a well drilling engineering of a mine in Shandong, the paper introduced the advantages and difficulties of construction without surface casing drilling with the countermeasures. The construction of 2 wells were fulfilled ahead of time through deviation control by tower drilling tools, inclination survey by gyro inclinometer, wall protection by high-quality mud and working intensity reducing by buoyancy device and impact wrench. Drilling without surface casing greatly saved the construction cost.

    参考文献
    相似文献
    引证文献
引用本文

王英,刘炳志,杜庆军.大口径煤矿应用井施工技术难点及应对措施[J].钻探工程,2010,37(12):51-53.
WANG Ying, LIU Bing-zhi, DU Qing-jun. Technical Difficulties in Large Diameter Well Drilling in Coal Mine Construction and the Countermeasures[J]. Drilling Engineering, 2010,37(12):51-53.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2010-05-13
  • 最后修改日期:2010-05-13
  • 录用日期:2010-10-27
  • 在线发布日期: 2010-12-28
  • 出版日期: 2010-12-25
文章二维码