锦屏一级水电站地下厂房系统对穿预应力锚索孔孔斜控制施工技术
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Construction Technology of Hole Deviation Control for Horizontal Pre-stressed Anchor in the Underground Powerhouse System of Jinping First Stage Hydropower Station
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    锦屏一级水电站地下厂房洞室主机间、主变室、母线洞等洞室系统的边墙、蚀变岩段和较大断层采用了对穿预应力锚索加强支护。在对穿预应力锚杆的施工过程中,根据不同的地质地层段,采取严格的孔斜控制措施,并不断地改进控制方法,基本解决了对穿预应力锚索造孔孔斜控制的技术问题,满足了设计技术要求,积累了对穿预应力锚索孔斜控制施工经验。

    Abstract:

    Reinforced support was made for the side wall, altered rock and large fault of the main engine compartment, main transformer room and bus cavern in underground powerhouse of Jinping 1 hydropower station by the horizontal pre-stressed anchor. In the construction process of pre-stressed horizontal anchor, according to the different geological formations, hole deviation was basically solved by strict control methods with continuous improvement.

    参考文献
    相似文献
    引证文献
引用本文

张涌泉,李朝华.锦屏一级水电站地下厂房系统对穿预应力锚索孔孔斜控制施工技术[J].钻探工程,2010,37(11):64-66.
ZHANG Yong-quan, LI Chao-hua. Construction Technology of Hole Deviation Control for Horizontal Pre-stressed Anchor in the Underground Powerhouse System of Jinping First Stage Hydropower Station[J]. Drilling Engineering, 2010,37(11):64-66.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2010-03-30
  • 最后修改日期:2010-03-30
  • 录用日期:2010-04-14
  • 在线发布日期: 2010-11-24
  • 出版日期: 2010-11-25
文章二维码