Three-bench Seven-step excavation is the development of threebench excavation, which is more and more applied in large section tunnel construction. Take the engineering case of Xiangmuwan tunnel of LanzhouChongqing railway, the excavation characteristics, construction organization, technological process and construction key points were introduced in detail.
参考文献
相似文献
引证文献
引用本文
李海波.三台阶七步开挖法在大断面隧道施工中的应用[J].钻探工程,2010,37(9):78-80.LI Hai-bo. Application of Three-bench Seven-step Excavation Method in Large Section Tunnel Construction[J]. Drilling Engineering, 2010,37(9):78-80.