According to the characteristics of lost circulation in drilling in Zhenjing oil field, the treatment methods were adopted for different cases. Time-controlled drilling and short pipe-trip was for the lost circulation in the quaternary loess layer, prevention and drilling with unidirectional pressure temporary plugging additive was for the lost in permeable sand-stone layer, composite cement slurry was for vertical fracture layer and bridge material + cementing was for serious loss. All of these lost circulation control technologies were proved effective.
参考文献
相似文献
引证文献
引用本文
俞宪生.鄂尔多斯盆地镇泾工区钻井堵漏技术措施[J].钻探工程,2009,36(6):19-20,23.YU Xian-sheng. Lost Circulation Prevention in Zhenjing Oil Field of Erdos Basin[J]. Drilling Engineering, 2009,36(6):19-20,23.