Currently in the whole world, Beypazari trona solution project is the largest mining engineering with the methods of solution mining and intersected well drilling. Due to the geological condition changes and abnormal earth magnetism behavior, some abnormal deviations happened with the MWD device. An in-situ probe calibration work is designed and preformed so as to find what influences the probe measurement precision. The calibration results show the assembly condition of MWD probes greatly contributes the deviation of measurement, thus some measures are necessarily taken to prevent from such errors in the well drilling construction.
参考文献
相似文献
引证文献
引用本文
胡汉月 向军文 董迪壮.土耳其贝帕扎里天然碱矿钻井工程MWD实地校核[J].钻探工程,2007,34(7):1-4.HU Han-yue, XIANG Jun-wen, DONG Di-zhuang. An In-situ Calibration on MWD Probes at Beypazari Trona Mining and Drilling Site[J]. Drilling Engineering, 2007,34(7):1-4.