How to determine the length of power-injected pile is a important problem in practical project. Considering the complex special distribution of soft earth stratums in fact, the length of pile by prospecting will be unsatisfied to the requirement of improvement. The author participated in a project of improvement of soft ground by power-injected pile, put forward controlling the length of pile by the intensity of working current, put it in practice and succeeded considerable technical and economic benefits. The experimental data and conclusion from engineering project is valuable to similar projects.
参考文献
相似文献
引证文献
引用本文
任海军,张可能,刘杰.根据施工电流值控制粉喷桩桩长的现场试验研究[J].钻探工程,2005,32(3):12-15.REN Hai-jun, ZHANG Ke-neng, LIU Jie. Site Test Research on Length Control of Power-injected Pile According Electricity in Working[J]. Drilling Engineering, 2005,32(3):12-15.