The diameter of the diversion tunnel of Xiaolangdi project is 14.5 m. Drilling problem is solved by using drilling and grouting carrier with concentric gear as well as steering track system. So there's a successful model for large diameter drilling and grouting construction.
参考文献
相似文献
引证文献
引用本文
李志刚,崔雪玉.小浪底工程导流洞大洞径固结灌浆施工台车的设计与运行[J].钻探工程,1999,(3):34-35.Li Zhigang, Cui Xueyu. Design and Operation of the Carrier for Consolidation Grouting in Large Diameter Diversion Tunnels of Xiaolangdi Project[J]. Drilling Engineering, 1999,(3):34-35.