This article introduces tthe technical problems in comstruction of 2.20m .diameter rock embedded pile,including building of platform, once hole completion technique with drag bit and rock bit penertating hard rock,treating muff breaking at off-shore area by using flush fluid balance principle and improving flowsheet of grouting to gaurantee the quality.
参考文献
相似文献
引证文献
引用本文
柴云来.泥湾门大桥浅海大直径嵌岩桩施工技术[J].钻探工程,1994,(3):28-29,31.Chai Yunlai. Construction Technology of Large-diameter Pock Embedded Foundation Pile in Niwanmen Bridge[J]. Drilling Engineering, 1994,(3):28-29,31.