深部咸水层CO2地质封存钻井施工技术研究——以山东省首个咸水层CO2地质封存项目为例
CSTR:
作者:
作者单位:

1山东省地质矿产勘查开发局第二水文地质工程地质大队(山东省鲁北地质工程勘察院);2山东科技大学地球科学与工程学院

作者简介:

通讯作者:

中图分类号:

P634;X51

基金项目:

山东省地质矿产勘查开发局2022年度地质勘查引领示范与科技攻关项目(编号:鲁地字〔2022〕15号)


Research on drilling construction technology for CO2 geological storage in deep saline aquifers: A case study of the first CO2 geological storage project in deep saline aquifers in Shandong Province
Author:
Affiliation:

1山东省地质矿产勘查开发局第二水文地质工程地质大队(山东省鲁北地质工程勘察院),山东 德州 2530721The Second Institute of Hydrogeology and Engineering Geology, Shandong Provincial Bureau of Geology & Mineral Resources (Lubei Geo-Engineering Exploration Institute of Shandong Province), Dezhou Shandong 253072, China;2山东科技大学地球科学与工程学院,山东 青岛 2665902College of Earth Science and Engineering, Shandong University of Science and Technology, Qingdao Shandong 266590, China

Fund Project:

山东省地质矿产勘查开发局2022年度地质勘查引领示范与科技攻关项目 鲁地字〔2022〕15号山东省地质矿产勘查开发局2022年度地质勘查引领示范与科技攻关项目(编号:鲁地字〔2022〕15号)

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    井孔是CO2注入目标层位的通道,是对注入地层中的CO2及其对地层影响进行长期监测研究的基础和关键。相比常规的地热钻井,深部咸水层CO2地质封存钻井需满足更高的密封性与耐腐蚀要求。本研究以山东省首个咸水层CO2地质封存项目为例,列举了钻井施工难点,提供了主要的技术对策,为其他地区咸水层CO2地质封存项目钻井施工提供依据。研究结果表明,钻井施工过程中采取快速钻进及相应钻井液护壁技术,解决井壁稳定性差问题。通过在取心管底部增加防止岩心掉落的卡簧装置,解决取心难的问题。采用高强度套管成井解决套管的气密性与安全性问题。采用BCE?750S型防腐蚀水泥固井射孔成井工艺,解决固井水泥腐蚀性问题。通过在CO2注入管柱增加卡瓦封隔器装置,保障CO2注入的气密性与稳定性。同时,采用石油开采领域的采油树井口装置,并安装压力监测表,解决井口装置长期承压及监测问题。

    Abstract:

    The wellbore serves as the pathway for CO2 injection into the target formation and constitutes the fundamental basis for long-term monitoring and research on both the CO2 injected into the formation and its impact on it. Compared with conventional geothermal drilling, the wellbore of CO2 geological storage in deep saline aquifers requires higher standards of sealing and corrosion resistance. This study takes the first CO2 geological storage project in deep saline aquifers in Shandong Province as an example, the difficulties in drilling construction are listed, the main technical countermeasures are offered, and guidance for drilling construction of other CO2 geological storage projects in deep saline aquifers is provided. The research results show that during the drilling construction process, the rapid drilling and corresponding mud wall protection technologies are adopted to solve the problem of poor wellbore stability. The difficulty of core sampling was solved by adding a spring clip device to prevent core from falling at the bottom of the coring tube. High-strength casing is used to solve the gas tightness and safety problems of the casing. The integrated technology of cementing, perforating and well completion using BCE-750S anti-corrosion cement is adopted to solve the problem of cement corrosion. By adding the slips packer device to the CO2 injection pipe string, the gas tightness and stability of CO2 injection are guaranteed. At the same time, the oil wellhead device in the oil production field is adopted, and a pressure monitoring instrument is installed to solve the long-term pressure-bearing and monitoring problems of the wellhead device.

    参考文献
    相似文献
    引证文献
引用本文

王世浩,王玲丽,王勇军,等.深部咸水层CO2地质封存钻井施工技术研究——以山东省首个咸水层CO2地质封存项目为例[J].钻探工程,2026,53(S1):333-338.
WANG Shihao, WANG Lingli, WANG Yongjun, et al. Research on drilling construction technology for CO2 geological storage in deep saline aquifers: A case study of the first CO2 geological storage project in deep saline aquifers in Shandong Province[J]. Drilling Engineering, 2026,53(S1):333-338.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2026-05-11
  • 最后修改日期:2026-07-17
  • 录用日期:2026-07-24
  • 在线发布日期: 2026-10-29
  • 出版日期: 2026-10-20
文章二维码